A maintenance order is the plant's work order: which resource, which operations in which sequence, which parts and people, planned and actual dates, and what was found.
- Where
- Plant Maintenance › Process › Maintenance Order
- Who uses it
- The maintenance planner, the technician
- When
- When maintenance work is decided
- Needs first
- Maintenance Category, Resource, Operation
What it is for
- Category, Site and Resource are required; status starts Open.
- Operation tab: at least one line ("Operation Lines cannot be empty"); each with an operation and a duration above zero. Open Requirement and Items on a line for its resources and parts.
- Item tab: the parts of the whole order, each with item, units and quantity above zero.
- Resource tab: the people or machines booked, with dates and hours.
- Damage Code tab: damages found.
- An order of category PLM shows the Maintenance Plan button on the operation grid: pick due visits of a Maintenance Plan - Schedule for the order's resource; their operations and parts fill the lines.
- When the category has Required Maintenance Notification, Notification Request is required.
- Break Down ticked locks Duration In (Hour).
The order posts nothing and does not reserve or issue stock.
Every field in plain words
General
| Field | What it means | What to put |
|---|
| Maintenance Order | The number of the order | Given by the number range, or typed. Cannot be changed once saved |
| Maintenance Category | The kind of maintenance: breakdown, preventive, planned | Pick from Maintenance Category. Required. Cannot be changed once saved |
| Maintenance Order Status | Where the order stands. New orders start Open | Pick from the list |
| Block | Stops the record from being picked on new documents | Leave clear while it is in use |
Object Identification
| Field | What it means | What to put |
|---|
| Site | The site | Pick a site. Required. Cannot be changed once saved |
| Resource | The resource: a machine, a person, a tool | Pick a resource. Required. Cannot be changed once saved |
| Name | Name of the resource | Fills in by itself |
| Resource Type | Type of the resource | Fills in from the resource |
| Resource Group | The resource group | Fills in by itself |
Component Identification
| Field | What it means | What to put |
|---|
| Component | The component of the resource the work is on | Pick a component of the resource. Cannot be changed once saved |
| Component Description | Description of the component | Fills in by itself |
Internal Reference
| Field | What it means | What to put |
|---|
| Notification Request | The maintenance notification this order answers | Pick a notification. Required when the category asks for one |
Maintenance
| Field | What it means | What to put |
|---|
| Maintenance Type | Maintenance type | Pick from the delivered list. Cannot be changed once saved |
| Maintenance Sub Type | Maintenance sub-type | Pick from the delivered list. Cannot be changed once saved |
Controlling
| Field | What it means | What to put |
|---|
| Requester | Who asked for the work | Pick from the responsible persons list |
| Date | Date of the request | A date |
| Time | Time of the request | A time |
| Notes | A note on the document | Free text |
Malfunctioning
| Field | What it means | What to put |
|---|
| Date | When the malfunction started | A date |
| Time | Time the malfunction started | A time |
| Break Down | The object is broken down and not working | Tick for a breakdown |
| Duration In (Hour) | How long, in hours | A number |
| Problem | Short name of the problem | Free text |
| Problem Details | The problem in more words | Free text |
Resolution Expectation
| Field | What it means | What to put |
|---|
| Date | When a fix is expected | A date |
| Time | Time a fix is expected | A time |
| Reason | The reason | Pick a reason |
Planning
| Field | What it means | What to put |
|---|
| Maintenance Planner | The maintenance planner | Fills in by itself |
| Responsibility Central | The responsibility center | Pick a responsibility center |
| Responsible | The person responsible | Pick from the responsible persons list |
Planned Date & Time
| Field | What it means | What to put |
|---|
| Planned Start Date | Planned start | A date |
| Planned End Date | Planned end | A date, not before the planned start |
| Planned Start Time | Planned start time | A time |
| Planned End Time | Planned end time | A time |
| Planned Final Date | Planned final date | A date, not before the planned start |
Actual Date & Time
| Field | What it means | What to put |
|---|
| Actual Start Date | When the work really started | A date |
| Actual End Date | When the work really finished | A date |
| Actual Start Time | Actual start time | A time |
| Actual End Time | Actual finish time | A time |
| Actual Final Date | Actual final date | A date |
Technical Observation
| Field | What it means | What to put |
|---|
| Symptom | What the user notices | Pick a symptom |
| Symptom Area | Where the symptom shows | Pick a symptom area |
| Fault | The fault found | Pick a fault |
| Fault Area | Where the fault is | Pick a fault area |
| Damage | The damage found | Pick a damage |
| Damage Area | Where the damage is | Pick a damage area |
| Cause | Why it happened | Pick a cause |
| Cause Details | More words on the cause | Free text |
Operation
| Column | What it means | What to put |
|---|
| Sequence | Order of the line | A number |
| Operation | The operation (a unit of work) | Pick an operation. Required |
| Activity | Activity reference on the operation | Free text |
| Name | Name of the operation | Fills in by itself |
| Work Center | The work center | Pick a work center |
| Date From | Start of the period | A date |
| Date To | End of the period | A date |
| Duration Unit | Unit of the duration | Pick a unit, such as hours |
| Duration | How long the work takes | A number, in the duration unit |
| Duration Length Unit | Unit of the elapsed length | Pick a unit |
| Duration Length | Elapsed length of the work | A number |
| Responsible | The person responsible | Pick from the responsible persons list |
| Requirement | Resources needed for the operation | Open it and list them |
| Items | Items needed for the operation | Open it and list them |
| Line Text | A note on the line | Free text |
Item
| Column | What it means | What to put |
|---|
| Sequence | Order of the line | Fills in by itself |
| Item No | Spare part or material needed | Pick an item. Required |
| Item Variant | The item variant | Fills in by itself |
| Name | Name of the item | Fills in by itself |
| Required Unit | Unit the item is asked in | Pick a unit |
| Required Quantity | Quantity needed | A number greater than zero |
| Required Date | When the line is needed | A date |
| Required Time | Time needed | A time |
| Line Text | A note on the line | Free text |
Resource
| Column | What it means | What to put |
|---|
| Resource | The resource: a machine, a person, a tool | Pick a resource |
| Date From | Start of the period | A date |
| Date To | End of the period | A date |
| Time From | Start time | A time |
| Time To | End time | A time |
| Duration In (Hour) | How long, in hours | A number |
| Total Duration in (Hour) | Total hours of the line | Calculated |
| Line Text | A note on the line | Free text |
Damage Code
| Column | What it means | What to put |
|---|
| Damage | The damage found | Pick a damage |
| Damage Area | Where the damage is | Pick a damage area |
| Line Text | A note on the line | Free text |
Choose the categories and the default fields with Plant Maintenance Setting.
Scenarios
- A pump breaks down on the night shift. Order of the breakdown category for the pump, Break Down ticked, operations "dismantle" and "replace seal", the seal on the Item tab.
- The monthly compressor checks are due. Order of category PLM for each compressor; Maintenance Plan button; pick this month's visits.
What it is connected to
If something looks wrong
- Save is refused with "Operation Lines cannot be empty". Add an operation.
- Save is refused with "Maintenance Order: Operation Lines - Line ID: … - Duration cannot be Zero or Negative". Give a duration.
- Save is refused with "Maintenance Order: Item Lines - Line ID: … - Item cannot be Empty" (or Quantity, Required Unit, Inventory Unit, Factor). Complete the item line.
- Save is refused with "Maintenance Order - Planned Start Date cannot be greater than Planned End Date" (or Planned Final Date). Fix the planned dates.
- Save is refused with "Maintenance Order - Actual Start Date cannot be greater than Actual End Date". Fix the actual dates. The message about the Actual Final Date is checked against the Actual End Date in this release.
- Save is refused with "Maintenance Order: Operation Lines - Line ID: … - Date From cannot be greater than Date To". Fix the line dates.
- The Maintenance Plan button is missing. The category code is not PLM.
- Notification Request is required but the list is empty. The category requires a notification and notifications cannot be entered in this release. Clear the tick on the category.