Report the problem on a Notification Request if you use them, raise the Maintenance Order, and confirm each operation on Maintenance Order Confirmation.
Before you start
- Maintenance categories without Required Maintenance Notification (notifications cannot be entered in this release).
Steps
- Raise the order: category, site, resource; operations with durations; parts on the Item tab; people on the Resource tab. Save.
- Do the work. Issue spare parts from stock with an inventory issue (Item Issue); the order does not issue them.
- Confirm each operation: pick the order and operation, tick Completed or give the remaining work, record resource time and items used. Save.
Check it worked
- The Maintenance Order list shows the order; the confirmation form prints the confirmed operation.
If something looks wrong
- "Operation Lines cannot be empty" - add an operation.
- The operation is not offered on the confirmation. It is already confirmed as completed.