A measuring-based plan is meant for work due on usage (running hours, cycles) rather than on dates. It has the same parameters, strategy and operations as a time-based plan, without the scheduling dates.

Where
Plant Maintenance › Maintenance Plan › Maintenance Plan - Measuring Based
Who uses it
The maintenance planner
When
At setup
Needs first
Maintenance Strategy, Resource Reading Setup

What it is for​

A plan says which resources get which operations, on which cycles of a strategy.

  1. Fill the header and at least one Parameter (resource group, resource, key value, manufacturer or model): the plan covers every resource that matches all the parameters given. Create is refused otherwise ("Atleast one field select in Paramenters").
  2. Pick the Maintenance Strategy. On Create, its cycles become columns of the operation grid.
  3. On each operation line, switch on the cycles the operation belongs to. Open Items to list the parts the operation needs.
  4. Save. Then run Maintenance Plan - Schedule to produce the dated visits.

A schedule run copies the plan as it is at that moment; changing the plan later does not change a schedule already run.

In this release no screen compares readings with the plan to make work due: the schedule run counts periods from a start date, and this plan has no start date or period on its layout. Readings are recorded on Resource Reading.

Every field in plain words​

General​

FieldWhat it meansWhat to put
Maintenance PlanThe code of the planA short unique code. Required. Cannot be changed once saved
NameName of the planFree text. Required

Parameters​

FieldWhat it meansWhat to put
Resource GroupThe resource groupPick a resource group
ResourceThe resource: a machine, a person, a toolPick a resource
Key ValueKey value of the resourceFills in by itself
ManufacturerThe manufacturerPick from Manufacture
ModelThe modelPick from Model

Maintenance Strategy​

FieldWhat it meansWhat to put
Maintenance StrategyThe strategy whose cycles the plan usesPick from Maintenance Strategy. Cannot be changed once saved. Required. Cannot be changed once saved

Operations (Basic Data tab)​

ColumnWhat it meansWhat to put
OperationThe operation (a unit of work)Pick an operation
NameName of the operationFills in by itself
Duration UnitUnit of the durationPick a unit, such as hours
DurationHow long the work takesA number, in the duration unit
ItemsItems needed for the operationOpen it and list them

Items (opened from an operation line)​

ColumnWhat it meansWhat to put
Item NoThe item (part or material)Pick an item
NameName of the itemFills in by itself
UnitUnit of measurePick a unit
QuantityHow manyA number greater than zero
Line TextA note on the lineFree text

How to configure it​

Use it to record which operations belong to which usage cycle. Use the time-based plan where visits must be scheduled.

Scenarios​

  • A fleet of generators is serviced every 250 running hours. Record the plan here with the 250-hour cycle; schedule the visits by time until reading-driven scheduling exists.

What it is connected to​

If something looks wrong​

  • No visit becomes due when the meter passes the cycle. Not supported in this release.
  • Create is refused with "Atleast one field select in Paramenters". Give at least one parameter.