How do I work out what materials to buy for a plan?

On Material Requirement Planning pick the plan and date, tick Validate Available Stock and Create Purchase Requisition, Create, check, and Save.

Screen
Material Requirement Planning (Master Planning)
Who
The planner or buyer
Takes effect
On Save
Needs first
A master plan; warehouses marked Required in MRP

Before you start​

  • A Master Planning document.
  • Warehouses marked Required in MRP (Warehouse).
  • Safety Lead Time, Minimum Order Quantity and Order Multiple on the items, if wanted.

Steps​

  1. Open Material Requirement Planning, pick the Plan and the Transaction Date.
  2. Tick Validate Available Stock, and Create Purchase Requisition and/or Create Manufacturing Order. Fill Purchase Reason and responsibles.
  3. Create. The requirement, summary and order lines fill in.
  4. Save. Requisitions and Planned manufacturing orders are raised.

Check it worked​

  • Draft purchase requisitions appear in purchasing with the MRP number; Planned orders on the Manufacture Order list.

If something looks wrong​

  • "Warehouses are not marked as Required in MRP" Mark them on the warehouse.
  • "There is no BOM of ... found in Transaction Date ..." A made component needs a valid BOM.