How do I work out what materials to buy for a plan?
On Material Requirement Planning pick the plan and date, tick Validate Available Stock and Create Purchase Requisition, Create, check, and Save.
Before you start
- A Master Planning document.
- Warehouses marked Required in MRP (Warehouse).
- Safety Lead Time, Minimum Order Quantity and Order Multiple on the items, if wanted.
Steps
- Open Material Requirement Planning, pick the Plan and the Transaction Date.
- Tick Validate Available Stock, and Create Purchase Requisition and/or Create Manufacturing Order. Fill Purchase Reason and responsibles.
- Create. The requirement, summary and order lines fill in.
- Save. Requisitions and Planned manufacturing orders are raised.
Check it worked
- Draft purchase requisitions appear in purchasing with the MRP number; Planned orders on the Manufacture Order list.
If something looks wrong
- "Warehouses are not marked as Required in MRP" Mark them on the warehouse.
- "There is no BOM of ... found in Transaction Date ..." A made component needs a valid BOM.