How do I plan production from sales orders?
On Master Planning copy the sales order lines in, save, then use Next Action Create Manufacturing Order.
Before you start
- Sales orders ready to process (Sales Order).
- The made items with a Manufacturing Unit.
Steps
- Open Master Planning, give the plan date, dates and manufacturing unit, then Create.
- Copy from the sales order on the toolbar and pick the lines. Each keeps its ordered quantity.
- Adjust Plan Quantity upwards if you want more, then Save.
- Next Action, Create Manufacturing Order. One Planned order is raised per line.
Check it worked
- The orders appear on the Manufacture Order list with the plan number.
If something looks wrong
- "... has no Bill of Material lines on a Sales Order ..." Make that order by hand, picking the plan.
- "... has no Production Unit ..." Set the item's Manufacturing Unit.