Routing
A routing: for one item, the operations in sequence, and on each the resources with their hours and cost per hour.
What it is for
A Bill Of Material or Formula names its routing, and the Manufacturing Order copies the routing's operations and resources. On the confirmation the actual hours of each resource are entered and their cost is posted.
On each operation line, the Resource link opens the resources. For each resource: the hours of setup, run, wait and move, and Standard Cost Per Hour; Total Cost is the hours times the cost. The operation line shows Total Hours and Total Cost, and the header sums them.
Rules: Valid To may not be before Valid From, the routing needs at least one operation line, every operation line needs a resource, Sequence must be above zero and hours may not be zero or negative. Clone is allowed.
Every field in plain words
Header
| Field | What it means | What to put |
|---|---|---|
| Routing | The short code. | Cannot be changed once saved. Required |
| Item No | The item made. | An item of Type BOM or FOR. Required |
| Item Variant | The variant, if any. | Optional |
| Name | Its name. | Filled in. Required |
| Quantity | The quantity the routing is for. | Above zero |
| Total Hours | Sum of the lines. | Calculated |
| Total Cost | Sum of the lines. | Calculated |
| Alternate | An alternate routing. | As needed |
| Standard Cost | Standard cost. | Calculated |
| Approved | Approved. | Tick |
| Approved By | Who approved. | Pick a person |
| Site | The site. | Pick one. Required |
| Project | A project. | Optional |
| Valid From | Valid from. | A date |
| Valid To | Valid until. | A date |
| Block | Marks the record as blocked. | Tick to retire it |
Operations
One line per operation.
| Field | What it means | What to put |
|---|---|---|
| Operation | The operation. | Pick one |
| Name | Its name. | Filled in |
| Sequence | The order. | Above zero |
| Sequence Rule | How it follows the previous one. | Pick one |
| Total Hours | Hours of its resources. | Calculated |
| Total Cost | Cost of its resources. | Calculated |
| Resource | Link. Opens the resources of this operation. | |
| Line Text | A note on the line. | Any text |
Resource (behind the Resource link)
The resources of one operation.
| Field | What it means | What to put |
|---|---|---|
| Resource Group | The resource group. | Pick one |
| Name | Its name. | Filled in |
| Resource | The resource: a machine or a crew. | Pick one |
| Name | Its name. | Filled in |
| Fixed | Hours do not grow with quantity. | Tick for fixed time |
| Sequence | Order within the operation. | Above zero |
| Set Up Time In Hour | Setup hours. | Hours |
| Run Time In Hour | Run hours. | Hours |
| Wait Time In Hour | Wait hours. | Hours |
| Move Time In Hour | Move hours. | Hours |
| Standard Cost Per Hour | Cost per hour. | An amount |
| Total Cost | Hours times cost. | Calculated |
| Line Text | A note on the line. | Any text |
How to configure it
There is nothing to configure beyond the fields above. Which fields are shown, required or hidden can be changed per company by the consultant in the screen configuration.
Scenarios
- A furniture maker cuts, assembles and polishes, each on its own machine and crew. Three operations; on each, the machine and the crew with their hours and hourly cost.
What it is connected to
- Operation - the steps
- Bill Of Material - names the routing
- Manufacturing Order - copies it
- Manufacture Order Confirmation - actual hours and cost
- Resource - resources and their accounts
If something looks wrong
- "Production Routing - Valid To cannot be smaller than Valid From" Fix the dates.
- "Operations Lines cannot be empty" Add an operation.
- "Basic Data - Line ID: ... - Resource cannot be empty" Open the Resource link and add a resource.
- "Production Order - Quantity cannot be zero or less then zero" Enter a quantity.
- "Sequence cannot be zero or negative" / "Hour cannot be zero" / "Hour cannot be negative" Fix the sequence or the hours.