Resource

A resource is something that does work and costs money by the hour: a machine, a person, a work centre. It belongs to a resource group, sits at a site, and carries its hourly cost, calendar and capabilities.

Where
Organizational Structure › Resource; Product Information › Resource; Manufacturing › Resource; Project Accounting › Resource (OSRS)
Who uses it
The production planner
When
Once, while the company is being set up, and whenever a new one is needed
Needs first
Resource Group, sites in Inventory

What it is for​

Resource Type, Resource Group and Sub Group are chosen before Create and locked afterwards. On Create the costing lines, the hourly cost and the unit text are copied from the group; changing Standard Cost Per Hour on a line re-adds Per Hour Cost.

What the screen shows depends on the type: the machine type (code M) adds the Component and Machine Details tabs; the person type (code W) shows Employee, and picking an employee fills the resource code and name from it; only the type with code L can be ticked Work Center.

Every field in plain words​

General​

FieldWhat it meansWhat to put
ResourceThe resource code.Typed on New, or filled from Employee. Locked after Create.
NameThe resource’s name.Required.
Resource TypeThe type of resource.Required. Fixed list. Locked after Create.
Resource GroupThe group it belongs to.Required. Locked after Create.
Resource Sub GroupIts sub group.Optional. Locked after Create.
QuantityHow many of this resource there are.A number. Movements in and out change what is available.

Costing​

FieldWhat it meansWhat to put
Unit Of Measure, TextThe unit the resource is measured in, as text.Required unless the type is L. Copied from the group.
Time Per Resource UnitTime one unit takes.Optional. A number.
Per Unit QuantityQuantity per unit.Copied from the group.
Per Hour CostCost per hour.The sum of Standard Cost Per Hour on the costing lines.
SiteThe site where the resource is.Required. Pick from the Site list.
Manufacturing UnitThe manufacturing unit it belongs to.Optional. Pick from the Manufacturing Unit list.
Work CenterThe resource is a work centre.Only for type L.
Work CenterThe work centre this resource works in.Optional. Pick from the list.

Costing​

Costing lines, copied from the group on Create.

ColumnWhat it meansWhat to put
Cost ObjectA cost object.Optional. Pick from the Cost Object list.
NameIts name.Optional.
Standard Cost Per HourIts cost per hour for this resource.Optional.
Line TextA note.Optional.

Machine Details​

FieldWhat it meansWhat to put
Resource LocationWhere the machine is installed.Optional. Pick from the list.
Key ValueA key value.Locked after the first save.
ManufacturerMaker.Optional. Pick from the Manufacture list.
ModelModel.Optional. Pick from the Model list.
Part NumberPart number.Optional.
Country of ManufactureCountry of make.Optional. Pick from the Country list.
Month of ConstructionMonth built.Optional.
Year of ConstructionYear built.Optional.
Serial NumberSerial number.Optional.
Acquisition ValueWhat it cost.Optional. A number.
Acquisition CurrencyCurrency of that cost.Optional. Pick from the Currency Legal Entity list.
Acquisition DateWhen it was bought.Optional. A date.
Warranty StartCustomer warranty start.Optional. A date.
Warranty EndCustomer warranty end.Optional. A date.
Inherit WarrantyCustomer warranty inherited.Tick or leave clear.
Master WarrantyCustomer master warranty.Optional.
Pass on InventoryPass the customer warranty on.Tick or leave clear.
Warranty StartVendor warranty start.Optional. A date.
Warranty EndVendor warranty end.Optional. A date.
Inherit WarrantyVendor warranty inherited.Tick or leave clear.
Master WarrantyVendor master warranty.Optional.
Pass on InventoryPass the vendor warranty on.Tick or leave clear.

Component​

Component (machine type).

ColumnWhat it meansWhat to put
ComponentA component of the machine.Optional. Pick from the list.
Component DescriptionIts description.Optional.
Line TextA note.Optional.

Calendar​

Calendar.

ColumnWhat it meansWhat to put
CalendarThe working calendar for a date range. Required.Required. Pick from the Calendar list.
Date FromFrom. Required.Required.
Date ToTo. Ranges of different calendars may not overlap.Optional.

Resource Capability​

Resource Capability: what the resource can do. Nothing reads this grid today.

ColumnWhat it meansWhat to put
Resource CapabilityA capability, from Resource Capability.Required. Pick from the Resource Capability list.
LevelThe level of that capability.Required.

How to configure it​

The screen allows import, so a long list can be loaded from a file instead of typed. Which fields are required, greyed, hidden or pre-filled for a company is set on Organizational Structure Setting, in its Default Parameters grid, and one user can differ through User Parameter Value.

What it is connected to​

If something looks wrong​

  • “Date From cannot be after Date To” A calendar line ends before it starts.
  • “Calendar - Line ID: … overlaps with Line ID: …” Two calendar lines overlap.
  • The Component and Machine Details tabs are missing. They show only for the machine type.