Manufacture Operation Confirmation
The confirmation of one operation of a manufacturing order. Each operation issues what it consumes and posts its resource cost; the last operation in sequence also receives the output.
What it is for
The same screen as Manufacture Order Confirmation, with Operation and Sequence on the header: only that operation's resources come in. Save issues components and posts resource cost as on the order confirmation. The output is received and added to the order only when the operation is the last in sequence; it may not confirm more than the operations of that last sequence have confirmed, nor more than the previous operation confirmed.
This screen does not offer Reverse.
Every field in plain words
Header
| Field | What it means | What to put |
|---|---|---|
| Confirmation | The confirmation number. | Given on Create. Required |
| Posting Date | Posting date. | Same as the confirmation date |
| Manufacturing Category | From the order. | Filled in |
| Notes | Notes; also the text of the postings. | Any text |
| Operation | The operation confirmed. | Pick one. Required |
| Name | Its name. | Filled in |
| Manufacturing Order | The order being confirmed. | A released order. Required |
| Confirmation Quantity | How much is confirmed now. | Up to what is left |
| Confirmation Date | The date; it is also the posting date. | Not before the order date. Required |
| Confirmation Date | Confirmation date. | |
| Confirmation Time | Time. | |
| Responsible | Who confirms. | Pick a person |
| Sequence | Its sequence. | Filled in. Required |
Confirm
What came out: the item, and co-products or by-products.
| Field | What it means | What to put |
|---|---|---|
| Item No | Item. | From the order |
| Item Variant | Variant. | |
| Name | Name. | Filled in by the system |
| Type | Type of output. | Filled in by the system |
| Unit | Unit. | |
| Quantity | Quantity. | The output lines must add up to Confirmation Quantity |
| Quantity Status | Good, Reject or another status. Good and Reject lines are received into stock. | Pick one. Required |
| Site | Site. | Required. Required |
| Warehouse | Warehouse it goes into. | Required. Required |
| Batch/Serial Number | Batch of the output. | When the item is batch-tracked |
| Batch Date | Batch date. | When required |
| Batch Expiry Date | Expiry. | When required |
| Best Before Date | Best before. | When required |
| Line Text | A note on the line. | Any text |
Consume
The components used.
| Field | What it means | What to put |
|---|---|---|
| Item Category | Category. | Filled in by the system |
| Item No | Component. | From the order |
| Item Variant | Variant. | |
| Name | Its name. | Filled in |
| Unit | Unit. | Filled in by the system |
| Actual Quantity | What was actually used. | A quantity |
| Plan / Actual Variance | Plan minus actual. | Calculated |
| Variance Reason | Why it differs. | Any text |
| Site | The site. | Pick a site. Required |
| Warehouse | Warehouse it is taken from. | Required. Required |
| Batch/Serial Number | The batch used. | Pick an available batch |
| Flushing Indicator | B: issued automatically on Save; M: issue it yourself. | From the BOM or the setting |
| Line Text | A note on the line. | Any text |
Resource
The operations and their resources. The Resource link opens the hours.
| Field | What it means | What to put |
|---|---|---|
| Operation | Operation. | Filled in by the system |
| Name | Name. | Filled in by the system |
| Resource | Resource. | |
| Sequence | The order of the step. | A number. Filled in by the system |
| Name | Name. | Filled in by the system |
| Sequence Rule | Rule. | Filled in by the system |
| Unit | Unit. | Filled in by the system |
| Plan Hour | Planned hours. | Filled in by the system |
| Plan Hour | Planned hours. | Filled in by the system |
| Actual Hour | Actual hours. | Hours |
| Actual Hour | Actual hours. | Filled in by the system |
| Additional Hour | Extra hours. | Filled in by the system |
| Hour Variance | Variance. | Filled in by the system |
| Plan Cost | Planned cost. | Filled in by the system |
| Warehouse | Warehouse. | |
| Resource | Link. Opens the resource hours and cost. | Filled in by the system |
| Line Text | A note on the line. | Any text |
Resource hours (behind the Resource link)
Planned and actual hours per resource; the actual cost of setup, run, wait and move time is posted.
| Field | What it means | What to put |
|---|---|---|
| Resource Group | Group. | |
| Name | Name. | Filled in by the system |
| Resource | Resource. | |
| Unit | Unit. | Filled in by the system |
| Sequence | Sequence. | Filled in by the system |
| Fixed | Fixed time. | Filled in by the system |
| Plan Hour | Planned. | Filled in by the system |
| Actual Hour | Actual. | Hours |
| Hour Variance | Variance. | Filled in by the system |
| Plan Cost | Planned cost. | Filled in by the system |
| Line Text | A note on the line. | Any text |
How to configure it
As for the order confirmation.
Scenarios
- A garment factory confirms cutting, stitching and finishing separately. One operation confirmation per stage; finishing, the last, receives the garments.
What it is connected to
- Manufacture Order Confirmation - the whole-order confirmation
- Routing - operations and sequence
- Manufacturing Order - the order
- Plan to produce - the manufacturing process this confirmation is a step of.
If something looks wrong
- "You cannot Confirm ... Quantity, Previous Operation Confirmation is ..." Confirm the previous operation first.
- "You cannot Confirm ... Quantity, This Operation is already confirm ... Quantity" Less is left on this operation.
- "Your Last Sequence Operation Confirmation is Less ..." Another operation of the last sequence has confirmed less.
- "Production Order not found" Pick a valid order.
- "Confirmation date cannot be smaller then Production Date" Use a date on or after the order date.
- "Component Lines Data cannot be Empty" Add output lines.
- "Confirm Quantity is not matching with Confirm lines" The output and co-product lines must add up to Confirmation Quantity.
- "Production Confirmation - Line ID: ... - Unit cannot be Empty" Fill the unit of the consumption line.
- "Confirm - Line ID: ... - Confirm Quantity: ... cannot exceed Production Order Quantity: ..." More than what is left on the order.
- "Please Define Issuance Journal in Setting" Set Journal For Issuance on the manufacturing setting.
- "Please Define Resource Journal in Setting" Set Journal for Resource.
- "Resource ... Debit Account is not Configured" / "... Credit Account is not Configured" Give the resource its accounts (company setup).
- "Serial Production is not configured" A serial-tracked output cannot be confirmed.
- "Batch Number is Mandatory" / "Batch Date is Mandatory" / "Batch Expiry Date is Mandatory" / "Batch Before Date is Mandatory" Fill what the item's tracking structure asks for.
- "Production Item ... Default Warehouse is not defined" Give the item a default warehouse.
- "Item: ... Manufacturing Type is not defined in Item in Legal Entity" Set Type on the item.
- The finished good did not come into stock. Journal For Receive is empty on the setting; nothing is received automatically. Receive it on the production receipt screen in inventory.