How do I charge purchased material to a project?
Tick Auto Issue for Project on Project Accounting Setting and give each purchase order journal its issue journal on the Movement tab. A receipt against a purchase order that names a project then issues its item lines to the project on Save.
Steps
- Open Project Accounting Setting. Tick Auto Issue for Project.
- Movement tab: one line per purchase order journal used for project purchases, with its Journal For Issuance.
- On the purchase order, name the project.
- Save the receipt as usual. The issue to the project is made with it.
Check it worked
- Project Profitability shows the issued items as Actual Cost.
- The board tile Project cost by source shows them under material.
The issue is an ordinary stock issue document. What it posts is described with the inventory documents: see Inventory how-to.
If something looks wrong
- Nothing was issued. Auto Issue is off, the Movement tab is empty, the purchase order names no project, or the lines are not items.
- Items in store are used on a project. Issue them from stock naming the project. See Inventory how-to.