How do I budget and plan a project?
On Project Estimation type the activities, put them in a tree with Indent and Outdent, give each a Date From and Date To, and on each lowest activity open Requirement and list its needs with cost and sale price. The Gantt and Resources tabs draw themselves.
Steps
- Open Project Estimation, New. Number, Name, Date, Controller, Project. Create.
- Type the activities, one per line. Select a line and press Indent to put it under the one above.
- Give dates to each lowest activity.
- Click Requirement on each lowest activity. Add lines: Category, Unit, Quantity, Cost Price, Sale Price. Close: the activity's totals fill.
- Switch to Cost view to check cost, sale and profit up the tree. Save.
Check it worked
- The Gantt tab shows the schedule; the summary strip shows cost, sale, profit and duration.
- The Project Profitability list shows the estimate.
Nothing in this task posts to the accounts.
If something looks wrong
- "Requirement - Unit Cannot be empty". A requirement line with an item has no unit.
- Requirement does nothing. The line is a group: use the lines under it.