How do I agree prices with a vendor for a period?

Make a Purchase Agreement for the vendor and period, with the item-quantity commitment, and a line per item, unit and price. While it is valid, a purchase order line for that vendor, currency, item, unit and project takes the agreed price before the price list.

Screen
Purchase Agreement (Purchasing › Purchase Agreement)
Who
The purchase manager
Takes effect
On save, for orders dated inside the period

Steps​

  1. Open Purchase Agreement, New. Subject, Agreement Classification, Agreement Commitment (the item-quantity one), Vendor Account, Date From, Date To, Currency, and Project if it is for one project. Create.
  2. Add a line per item: Item No, Unit, Quantity, Price.
  3. Save.

Check it worked​

  • On a new purchase order for the vendor, the item's line shows the agreed price, with Purchase Agreement as its Price Origin.

If something looks wrong​

  • The order took the price list's price. The order's unit, currency, project or date does not match the agreement, or the commitment is not the item-quantity one.
  • Ordering more than the agreed quantity was not stopped. The agreement does not check quantities.