Billing Proposal

A Billing Proposal is what is billed now on a Project Contract. Choose the contract, and its billing lines come in with the quantity not yet billed. Lower a quantity to bill part of a line. Tax is worked out on each line.

Where
Project Accounting › Project › Billing Proposal
Who uses it
The project accountant
When
At each billing point of the contract
Needs first
A Project Contract with billing lines

What it is for​

The proposal records what has been billed against each contract line, so the contract knows what is still open. It is the Billed figure on the Project Profitability and Contract Billing Status lists.

The rule people get wrong: the proposal is the end of the module. It raises no customer invoice and posts nothing. The invoice is made on Customer Invoice in receivables.

Every field in plain words​

FieldWhat it meansWhat to put
Billing ProposalThe numberRequired
Billing Proposal DateThe date of the proposalRequired
CustomerWho is billedRequired. Only customers with a project contract
Customer for InvoiceWho the invoice would go toCopied from Customer and locked
Project ContractThe contract billedRequired. Only that customer's contracts. Choosing it fills the lines
ProjectNarrow the lines to one project of the contractOptional. Changing it fills the lines again
Posting DateThe proposal's posting dateRequired. The tax rates are taken on this date
Required DateWhen it is neededA date
Currency, Exchange Date, Exchange RateThe currencyDefaults to the company's currency; locked after Create
ResponsibleWho prepared itPick from the responsible list
Order Journal, Posting Profile, Responsibility CentralRecorded on the proposalNothing on save reads them
Tax ZoneThe tax zone for lines that have noneChosen at Create
Tax Exempt number, Price Including TaxRecorded on the proposal
Sales Area, Sales Organization, Sales Team, Customer ReferenceRecorded on the proposal
NotesAnything to rememberFree text

Lines​

ColumnWhat it means
Project, Project Billing, Sequence, Billing Line, CategoryFrom the contract line
Quantity, UnitThe quantity billed now. Comes in as the quantity still open; lower it to bill part
PriceFrom the contract line
Gross AmountQuantity x Price
Discount %, Discount AmountType either; the other follows. Comes in in proportion to the open quantity
Net Price, Net AmountAfter discount
Tax Zone, Tax GroupDecide the tax lines
Line TextA note

The Tax lines button shows a line's tax codes, percentages and amounts.

Totals​

Gross, Discount, Net, Tax and Landed Amount (net plus tax), each also in the company's currency at the exchange rate.

How it fills​

  1. Choose the Customer, then the Project Contract, and if you want one Project.
  2. Every billing line of the contract that still has an open quantity comes in, with the quantity not yet taken by earlier proposals and its amounts in the same proportion. A line with no quantity on the contract always comes in.
  3. Lower a quantity to bill part of a line, or delete lines not billed now.
  4. Save. The quantity on each contract line, added over this proposal, may not pass what was open.

Scenarios​

  • The second milestone of a building contract is reached. Choose the contract; the first milestone is fully billed and does not come in. Delete the third milestone line, save.
  • Twelve of 24 maintenance visits made. The visits line comes in with 24 open; lower it to 12.
  • The customer needs a tax invoice. Type it on Customer Invoice in receivables, with the proposal's amounts. Nothing carries the lines across.

What it is connected to​

If something looks wrong​

  • "Line ...: quantity ... is more than the ... still open on the contract." That contract line has less left to bill. Lower the quantity.
  • A contract line does not come in. It is fully billed on earlier proposals.
  • The customer is not in the list. The customer has no project contract.
  • No invoice appeared in receivables. A billing proposal makes none. Raise the invoice on Customer Invoice.